Case Study: BRADLEY-DOUBLELOCK Ltd
Bradley-Doublelock Ltd, is the UK’s market leader in the production of towing equipment and trailer parts.
They purchased their first Maylan Pallet Change System some years ago and have added recently two more units.
Thanks to the introduction of these units they have experienced an increase in output of 34%
and subsequently have been able to reduce labour requirements from five to two people
and component cycle time from 4.94 minutes to just 3.27 minutes.
Reduction in floor to floor times due to pallet system 34%
Components per Cycle (2 complete components per cycle) 4
Component Weight 3 Kg each
Fixture Weight 60 Kg
Total Weight 84 Kg
Material Cast Iron
Original Load/Unload time- 2 minutes
New Load/Unload time with Pallet System fitted- 10 seconds
Original floor to floor time for 4 parts- 9.88 minutes
New floor to floor time with Pallet System fitted- 6.54 minutes